• Day 1-14

    Survey engineer stakes house and does site plan

    City permit, fees and insurance
    Footing and foundation
    Rough in plumbing and electrical (raise foundation)

  • Day 14-30

    Framing the house starts
    Roof shingles
    Windows installed
    Rough in Electrical, plumbing and HVAC

  • Day 30-60

    Exterior siding

    Insulation
    Exterior trim
    Sheet Rock interior walls and ceiling

    < Day 14-30 Day 60-90 >
  • Day 60-90

    Interior trim and Doors
    Kitchen Cabinets
    Interior Paint

      Final Plumbing, HVAC and electrical

    • Day 90-120

      Floor Covering

      Appliances
      Driveway and sidewalk
      Grading and Landscaping